Troy Gully Sewage Pump Station Upgrade

Home / Completed / Troy Gully Sewage Pump Station Upgrade

trolly (1)

Troy Gully Sewage Pump Station Upgrade

Troy Gully Sewage Pump Station Upgrade involved upgrading a live sewage pump station while maintaining uninterrupted operation of existing assets. The project included installation and management of a major temporary bypass pumping system, construction works around live infrastructure, and confined space activities within operational wet wells.

Location
Dubbo, NSW
Client
Dubbo Regional Council

Technical Specifications

  • Capacity Upgrade: Increased  flow rate. 
  • Civil Construction: Deep penstock chamber construction and wet well structural modifications. 
  • Mechanical: Supply and installation of heavy-duty submersible sewage pumps and valves. 
  • Safety: Installation of custom access covers, grates, and handrails (AS 1657). 
Troy 2
Troy 3

Current Status

Completed

Handed over with comprehensive as-built drawings and operator training modules.